Structure of the bridge in a picture taken last April ... prolonged construction period has become a hot issue.
By ALFREDO P
HERNANDEZ
THE prolonged
construction period of a vital bridge in Parang, Mambulao, CamNorte, has
continued to draw hostile and friendly comments from local Mambulaoans and
those overseas.
This could be
skimmed on the Facebook account postings by members of the Jose Panganiban,
Camarines Norte Group who are monitoring the progress of the bridge project.
While some messages
showed impatience over the alleged delay in the work, others have vigorously
supported the way the project was being handled by the local government.
Supporters said the
whole process – from project planning and funding – has been transparent and
that they are happy that such an infrastructure is being put up for the good of
the community.
On the other hand,
others who had knowledge on how this kind of project is handled criticized the
pace the project is moving, one reason the targeted completion date was missed.
The old bridge was
closed to traffic on February 19 and actual construction work began at the end
of April after the old structure had been demolished and the work site cleared
of debris.
Reacting to the criticisms
sometime last June, the local government said the project is closely being
monitored.
The bridge costs at
least P22 million, of which P20 million came from the bridge program of the
President covering the major bridge parts, with the rest from the LGU as a
counter fund to pay for the cost of demolition of the old structure and
clearing.
Contractor NFH
Construction and Supply has been engaged to put up the bridge abutment.
NFH work timetable
was earlier upset when one of its cranes to lift heavy bridge parts failed to
come to the worksite as scheduled.
A source familiar
with the project posted on the same Facebook site to clarify that the P20
million funding could never be used on items outside the bridge project.
There had been
Facebook postings insinuating that the funds for the bridge were “misused” but
this was dismissed by the source, saying that “everything was above board”.
Vice-Mayor Ariel
Non, in his June 20 postings, said it would take 130 days for the bridge to be
completed from the time the worksite had been cleared of debris from the old
structure.
Counting from the
time work equipment was supposed to begin erecting the heavy concrete piles at
the start of last May, the work should be finished before this month is over.
With the bridge
closure, commuters from Parang bound for Mambulao poblacion take the long route
in tricycle via the Larap road and through Baranggay Plaridel, which sits on
the other side of the mangrove river opposite Baranggay Parang.
Tricycle operators
would normally charge a passenger P10 one way, although there have been
complaints that they are also charging at least P20 for each passenger.
The basic fare is P7
from Parang to the poblacion and vice versa.
Padilla apologized
for the delay in the bridge’s completion and appealed for understanding from
the community.
No comments:
Post a Comment